Riverview Drive Resurfacing (E Michigan to Gull)

  • Project value$689,897
  • Contractor nameReith-Riley Construction
A photo of Riverview Drive after paving

Riverview Drive will be resurfaced this year between E Michigan and Gull. This section of road was included in the jurisdictional transfer from the Michigan Department of Transportation and is in need of repair. In the longer term, we are planning to fully reconstruct this street and reimagine the corridor. This work in 2024 is meant to improve the street's condition and maintain it until the full reconstruction takes place, which we estimate will be about 10 years away. 

This project will include: 

  • Resurfacing Riverview Drive from E Michigan and Gull
  • ADA improvements to sidewalk ramps at intersections
  • Improving the intersection with Hotop with new signage and pavement markings 

Street work is expected to start in May and be finished in June. Sidewalk work may begin earlier in the spring before road construction.